Key points
- The alignment conflict between the Leh rail line and Dolan route highway in Manali has affected about 19 railway crossing points.
- The conflict has delayed the finalisation of the highway project and the implementation of an alternative traffic system.
- NHAI and Indian Railways have held high-level meetings, with a final resolution expected at the central ministry level.
The alignment of the proposed Leh rail line and the Dolan route highway in Manali intersects at multiple points, causing technical obstacles for both projects.
Approximately 19 railway crossing points are affected by this conflict, which has prevented NHAI from finalising the detailed plan for the Dolan route highway.

NHAI had requested Indian Railways to share the final alignment of the railway line for highway planning. However, NHAI alleges that Indian Railways declined to share this information, citing strategic and national interest concerns.
Due to the lack of available land for a four-lane road on the left bank, the right bank route remains in use. This route has suffered heavy damage because of the changing and violent nature of the Beas River.
NHAI had initially chosen the left bank as an alternative route due to the damage on the right bank. However, a proposed traffic system where vehicles travel to Manali via the right bank and return via the left bank cannot be implemented until the alignment issue is resolved.

High-level meetings have been held between NHAI and Indian Railways officials to resolve the deadlock. A final resolution is expected to come from a joint meeting at the central ministry level.
The proposed tunnel plan in Preeni has not advanced as of yet. Local residents may have to wait a long time for the development of the new left bank route.