- Central Minister Jagat Prakash Nadda said the Himachal Pradesh Government has failed to effectively use central funds for development projects.
- Delays were noted in the Bhanupalli-Bilaspur-Bari and Chandigarh-Baddi railway lines, as well as critical care blocks and health labs.
- The Centre has provided significant budgets for national highways, the Renuka Dam Project, and the Kishau Multipurpose Project.
Central Minister Jagat Prakash Nadda said on Friday in Bilaspur that the Himachal Pradesh Government has failed to utilise billions in financial assistance provided by the Centre, leading to delays in critical projects.
Nadda stated that the central government has provided a budget of more than ₹55,000 crore for national highways in the state. He added that timely implementation of projects is the responsibility of the state government and criticised delays in spending and land acquisition.
Regarding railway infrastructure, Nadda said the Bhanupalli-Bilaspur-Bari Railway Line has an estimated cost of ₹13,410 crore. The state government is required to pay ₹4,818 crore as its share but has deposited only ₹847 crore so far and has not yet acquired the land.
For the Chandigarh-Baddi Railway Line, which costs ₹1,540 crore, ₹1,160 crore has been spent. However, the state government has not yet deposited its share of ₹231 crore.
On healthcare, Nadda said the Centre provided ₹360 crore in 2021-22 to build nine critical care blocks, but only one has been completed. None of the 12 integrated health laboratories have been finished.
The Minister noted that under the 15th Finance Commission, ₹521 crore was made available to Himachal Pradesh, of which the state has spent ₹390 crore.
Nadda highlighted that while the Centre committed ₹1,000 crore for the Bulk Drug Park, Una, only ₹225 crore has been released and just ₹117 crore spent. He also mentioned that the Centre provided a budget of ₹7,000 crore for the Renuka Dam Project, ₹1,800 crore for Luhari Phase-1, and ₹15,624 crore for the Kishau Multipurpose Project.
The Minister stated that the Centre provided ₹100 crore for a Medical Devices Park, but the state government withdrew the proposal. He added that ₹1,422 crore has been given for the JaiKa Project, following a request from Chief Minister Sukhvinder Singh Sukhu. The Centre has extended the deadline for constructing critical care blocks and labs to March 2027.