Key points
- The Himachal Pradesh High Court cancelled the land acquisition process for the Bhanupalli-Bilaspur-Beri railway line.
- The acquisition covered approximately 538 bigha of land in Bilaspur district’s Sadar Tehsil.
- The court found the process did not meet requirements of the Land Acquisition Act, 2013 regarding reasons for extending acquisition deadlines.
The Himachal Pradesh High Court has cancelled the process of land acquisition for the Bhanupalli-Bilaspur-Beri broad gauge railway line. The court ruled that the initial notification issued on 29 March 2023, and subsequent notifications extending the deadline three times, were legally flawed.
The land acquisition was for approximately 538 bigha, 9 biswa and 0.5 biswansi in the villages of Upper Bheted, Barmana and Khthed in Sadar Tehsil of Bilaspur district.
The court found that the government did not follow proper procedure when extending the acquisition period. Under Section 19(7) of the Land Acquisition Act, 2013, written reasons for extending the period were required to be recorded, notified and uploaded to a website.
The government only cited ‘unavoidable administrative circumstances’ as the reason for delays in notifications. The court accepted that no real reason or details of the delay were recorded in files presented to it.
The High Court, a bench comprising Justice Ajay Mohan Goyal and Justice Yogesh Jaswal stated: “Simply mentioning administrative reasons to extend the time limit does not fulfill the requirements of the law.”
The same bench also said: “Citing administrative conditions without stating reasons is merely an excuse and cannot be legally accepted.”
The total length of the Bhanupalli-Bilaspur-Beri railway line is 63.1 kilometers. Of this, a section of 11.1 kilometers between Bilaspur and Beri remained to be acquired.
The revised estimated cost of the project is around 13,000 crore rupees. The initial estimated cost was 4,200 crore rupees.