Parbati-II Power Project Faces 10-Day Outage, Road Blockade Delays Repairs

A fault at the Addit-5 site and blocked access are hindering full power generation.

Key points

  • The Parbati-II Hydroelectric Project in Kullu is experiencing a 10-day outage of two 200-MW turbines.
  • A blocked road to the Addit-5 site is preventing repair teams and equipment from reaching the location.
  • Local villagers have submitted demands to NHPC, with construction work suspended pending a written agreement.

The Parbati-II Hydroelectric Project, which has a total installed capacity of 800 MW, is currently operating below its potential due to technical issues.

Two of the project’s four 200-MW turbines have been shut down for ten days following a fault in the air-pressure valve at Addit-5. The remaining two turbines are operating, but at reduced capacity because of limited water availability.

Access to the Addit-5 site is blocked by debris, preventing repair teams from reaching it. This has stalled the movement of heavy machinery, equipment and materials needed for repairs.

The NHPC technical team is preparing to carry out the necessary work at Addit-5, but a timeline for full restoration depends on assessing the valve’s condition and the scope of repairs.

The prolonged shutdown is impacting the project's revenue. Officials say that the project is unable to utilise its full installed capacity at this time.

Local villagers have submitted a 16-point charter of demands to NHPC, seeking compensation, road restoration, safety measures and employment opportunities.

Panchayat representatives report that NHPC agreed to these demands during a meeting at the power station. However, Raila-II Panchayat Pradhan Dabe Ram said construction work would remain suspended until NHPC provides a written agreement detailing the commitments.

According to Dabe Ram, elected head of Raila-II panchayat, “Construction would remain suspended until NHPC provided a written agreement covering the commitments. He warned of a ma…”