Land acquisition for Kangra airport expansion reaches 95 per cent

The project aims to extend the runway to allow larger aircraft like the Airbus A320 to operate.

Key points

  • Land acquisition for the Kangra airport expansion has reached 95 per cent across 14 revenue villages.
  • The runway will be extended from 1,372 metres to 3,010 metres to accommodate larger aircraft like the Airbus A320.
  • The total estimated cost for land acquisition and relief and rehabilitation is around ₹3,200 crore.

Land acquisition for the expansion of Kangra airport at Gaggal has reached nearly 95 per cent across 14 revenue villages in the Kangra and Shahpur subdivisions.

The project will increase the runway length from 1,372 metres to 3,010 metres. This will allow larger aircraft, including the Airbus A320, to operate at the airport.

Currently, only smaller aircraft such as the ATR-72 and Bombardier Dash 8 Q400 can land due to the short runway. The expansion is expected to improve connectivity between Kangra and major destinations and boost regional tourism potential.

Out of compensation awards worth ₹2,580 crore, an amount of ₹2,400 crore has been disbursed. The total estimated expenditure on land acquisition and relief and rehabilitation is around ₹3,200 crore.

BirD034-
File photo: Wojciech Kocot / Wikimedia Commons, CC BY-SA 4.0

For relief and rehabilitation, ₹215 crore has been disbursed, while ₹360 crore is yet to be paid. Possession of the acquired land has begun, and land in eight villages has been transferred to the Tourism Department.

The administration has sought a report on seven reportedly abandoned houses and 10 other houses identified during the acquisition and rehabilitation process.

Tourism Deputy Director Vinay Dhiman said, "Landowners can harvest their existing standing crops, but fresh sowing and new plantations are prohibited across all 14 revenue villages. Any violation will invite legal action."

Demarcation of land for the peripheral road has started. Boundary wire fencing around the expansion area, estimated to cost more than ₹1 crore, will be undertaken after funds are released.